Things went without much controversy I'm happy to say and they got everything wrapped up nicely and are on to their next job.
The roof gets water proofed tomorrow (which is good since rain is coming this weekend) and discussions are on going with Wally the HVAC guy. That is proving, thus far, to be the most challenging and frustrating part of the design process. The vents and returns can only go where they can go given where studs and joists are but at the same time we are trying to minimize or eliminate the number of bulk heads and/or double walls on the main floor. Some compromises will definitely have to be made. More pictures to illustrate this to come.
The new knee wall |
Adjusted partition wall by the front door |
The reinforced ceiling joists, slightly higher than before but no longer in danger of sagging further |
The current state of the main floor |